DCTA Positive Train Control
DCTA Projects & Plans
Proposal:
Positive Train Control Implementation
DCTA is committed to rail safety and has fully implemented Positive Train Control (PTC) as of 2020, the deadline set by the Federal Railroad Administration (FRA). PTC was designed to prevent collisions and other incidents by automatically detecting and controlling the movement of trains.
After multiple attempts to find a financially viable solution for implementing PTC, with input from outside consulting firms, DCTA decided to take a different approach. Critical to the success of DCTA’s new approach was soliciting industry feedback during the development of the technical approach to implement PTC, as well as seizing opportunities presented by the specific characteristics of the agency’s A-train system.
DCTA PTC Technology System Type:
DCTA installed Enhanced Automatic Train Control (E-ATC), a type of PTC system that uses an underlying automatic train control (ATC) system in conjunction with other “enhanced” features or systems to achieve the core required functionalities of PTC. The E-ATC system is designed to ensure train movement over properly aligned track switches, prevent overspeeding, prevent trains from running past stop signals and align train movements with restrictive operating conditions caused by track and road crossing conditions.
E-ATC also allows DCTA to leverage its fiber networks that enhance its existing signal system.
Current Status of PTC Implementation:
DCTA has been operating in full Positive Train Control mode since December 2020. The agency was the first in Texas to implement PTC on its entire commuter rail system.
Historical Timeline:
PTC Testing Begins
- May 2018
- DCTA begins PTC testing and identifies service modifications during the testing phase
DCTA Receives $4M in Funding
- September 2019
- DCTA receives $4 million in grant funding to help with the continued implementation of PTC testing and implementation
Revenue Service Demonstration (RSD) Begins
- January 2019
- DCTA begins RSD on limited trains with identified service modifications during the testing phase
PTC Testing Completes
- August 2019
- DCTA finishes PTC testing and implements PTC safety technology on all regular A-train service with passengers on board
RSD Competes
- September 2019
- DCTA finishes RSD and moves to extended RSD
PTC Safety Plan is Submitted
- April 2020
- DCTA submits its Positive Train Control Safety Plan (PTCSP) for FRA review and expects to receive FRA approval by December 31, 2020
DCTA is Certified by the FRA
- December 2020
- DCTA receives PTC certification from the FRA
Project Location:
640 State Highway 121
Lewisville, TX 75067